The naphtha
hydrotreater/continuous catalyst regeneration (NHT/CCR) platformer produces
reformate to be utilized as a blending stock in the gasoline pool (FIG. 1). In the
platformer, low-octane naphtha feed is converted to high aromatic reformate,
while producing hydrogen on platinum/alumina catalysts. It employs a suitable
catalyst and hydrogen to remove organic sulfur and nitrogen components that are
detrimental to CCR platformer catalysts.
The
catalyst is deactivated by coke deposition during the reaction. Deactivated
spent catalyst is continuously replaced with regenerated catalyst. The reactor
inlet temperature is designed for 548.89°C (1,020°F). Operational experience
has shown that, when the unit operates above 40,000 bpd, the second reactor’s
center pipe slowly plugs from the top down, and the reactor’s ΔP
increases slowly over time. Eventually, the reactor’s ΔP
increases to the point where feed maldistribution causes pinning of the catalysts
in the reactor. A 5-yr run length at 40,000 bpd is achievable; however, a 5-yr
run at 46,000 bpd or more was not possible without a shutdown to clean and
maintain the center pipe.
A
plan was needed to operate at a higher throughput of 50,000 bpd without causing
an excessive ΔP buildup in the second reactor. Based on a process revamp
study by the licensor to evaluate unit operation at 50,000 bpd and to limit
high-pressure buildup across the second reactor, a 20-in. partial bypass (FIG. 2) of feed
around the second reactor was required.
Problem statement. A detailed
examination of the challenges associated with the mechanical design, materials,
installation and field testing of a new 20-in. partial bypass line across the second
reactor inlet line was required. As the scope would need to consider the
existing brownfield environment, the following aspects would require special
attention:
Global piping stress and flexibility analysis. Using commercially available softwarea,
a static piping stress and flexibility analysis of the existing piping
configurations (based on as-built conditions) was completed in accordance with
ASME B31.3 requirements, using the beam elements with 6° of freedom. FIG. 3 illustrates
the 20-in. #300-rated bypass piping that connected each of the two 36-in. pipe
headers to and from the second reactor. The displacements and rotations of a global
stress model of the overall piping stress and flexibility of the entire 36-in.
reactor inlet/outlet lines of the second reactor were applied as “boundary conditions.”
In addition, all
loading scenarios related to the ASME B31.3 code were accounted for, based on
the environmental loads. The analysis was completed to evaluate SUS, OPE and EXP
stress categories, and these were found to be well within ASME B31.3’s
allowable limits. The piping support design was established based on the minimum
thermal expansion restraint provided by a constant spring hanger (CSH) that
could accommodate the 4-in. thermal travel and maintain the expansion stresses
within the code’s allowable limits, while simultaneously supporting the 20-in. bypass
piping and maintaining the sustaining stresses well within the allowable
limits. The CSH piping support is illustrated in FIG. 4.
Further to the static analysis, a modal (dynamic) analysis was also obtained,
utilizing commercial softwarea, to compute the low-frequency
flexural modes (the first 20 modes of natural frequencies) of the main pipework.
As the design based on the static analysis was found to be overly flexible,
minor support location adjustments were made. After multiple successive
iterations, the most optimum design of the support locations was established,
and these extremely low fundamental natural frequencies were eliminated from
the overly flexible piping system.
Once
the piping design based on global stress and related flexibility was
established, it was followed by a local stress analysis based on the following
methodology. For
each of the three identified load cases (SUS, OPE and EXP stress categories), the
three sets of nodal displacements (translations and rotations) for the
corresponding solid finite element model (FEM)—two nodes for the 36-in. header,
and one node each for the 20-in. branch pipe—were extracted from the static
stress results obtained from this commercial software’s analysis. These sets of
nodal displacements, which would be applied as the boundary conditions for each
of the corresponding three nodes of the solid model (two nodes for the 36-in.
header, and one node each for the 20-in. branch pipe), are shown in FIG. 5. The “local
FEM” using the 3D solid model is detailed in the following section.
Local stress analysis. The stress intensification factors (SIFs)
built into the commercial software’s program account for the stress
intensification, based on the configuration of the branch connection joint
between the 36-in. inlet header and the 20-in. bypass pipe in the global pipe
stress and flexibility analysis. Although the ASME B31.3 code for process piping
provides the reinforcement requirement calculations for the branch joints
between cross piping runs, it does not provide an additional framework to
investigate the local stresses at the branch connection in depth, if required. Using
commercially available softwareb in accordance with ASME Section
VIII Division 2 principles, a FEM-based stress simulation was completed, since
it was one of the most effective ways to evaluate this aspect.
The FEM with
continuum elements provided the total stress distribution for evaluation, and
the simulated stresses were compared with stress limits that are defined in the
ASME Section VIII Division 2 requirements. The 20-in. and 36-in. pipe materials
were of material specification ASTM A335 Gr-P11, and these properties were
utilized for the maximum allowable acceptable limits of induced stress. The
code stress checks were found to be well within ASME B31.3’s allowable limits,
as well.
Low-alloy 1.25Cr-0.5Mo piping material requirements. For the field
welds to be completed on the 36-in. reactor inlet header, the old/existing pipe
wall at the tie-in locations was thoroughly checked with ultrasonic testing (UT)
scans to ensure sufficient thickness and the absence of laminations or parent
metal defects prior to cutting. After the cutout of the hole for the branch
welds of the connecting 20-in. weldolet that was to be welded at the tie-in
location was completed with grinding and edge preparation, a dye penetrant test
(DPT) was conducted on the beveled edge of the hole in the 36-in. pipe to
detect the presence of any surface defects. Additional requirements applicable
to 1.25Cr-0.5Mo materials for services with operating temperatures over 440°C (825°F)
included:
The
low-alloy 1.25Cr-0.5Mo piping material required special attention regarding
procurement, fabrication and welding, inspection and testing. All welding was
required to be completed with welding and welders qualified in accordance with
ASME B31.3 and ASME Section IX. This welding was followed by a required post-weld
heat treatment (PWHT) as per code requirements. A thorough visual assessment of
the welds was completed, followed with a surface flaw-detection, non-destructive
examination (NDE) method of DPT.
Finally,
the weld-through-wall quality was ensured by completing a radiography test (RT)
of the weld. In general, RT was completed twice for all welds—once before the
PWHT, and after the PWHT to ensure the absence of any delayed cracking
associated with the material. The 36-in. x 20-in. branch welds were checked to confirm
the absence of any through-thickness weld-related defects by completing a true
volumetric NDE utilizing UT shear wave.
Integrity
testing requirements. To ensure the integrity of the fabricated 20-in. bypass header
piping, a shop hydrostatic pressure test was performed at the full code
requirement corresponding to the ASME B16.5 standard for #300-rated piping. The
hydrostatic pressure testing was performed after the completion of the PWHT.
For 1.25Cr-0.5Mo piping, the minimum metal temperature during pressure testing
was ensured to be at least 17°C (63°F) above the brittle-ductile transition
temperature of all pressure-retaining components at the time of pressure testing,
but not less than 15°C (59°F). Due to operational limitations posed by the
brownfield environment, it was not possible to subject the new piping to the
final field hydrotest due to the service conditions involving reactor
isolations and catalyst contamination. A pneumatic pressure test was completed per
the requirements of the original equipment manufacturer’s piping design—nitrogen
was used for the new 20-in. bypass, along with the connected 36-in. reactor
inlet lines.
Takeaway. This article has
provided helpful insights and guidelines on the critical aspects that should be
considered in a retrofit design of low-alloy 1.25Cr-0.5Mo piping material
employed in fabricating and installing the platformer reactor’s partial bypass
piping in a NHT plant. HP
NOTES
a Hexagon CAESAR II software
b Ansys software
Aslam Kittur is a mechanical engineer with expertise in troubleshooting integrity issues related to refinery static equipment. He now works in the technical services division of the global manufacturing administration area of Saudi Aramco’s downstream segment. Kittur has more than 23 yr of experience in the energy industry and specializes in performing stress analysis to understand the complex failure mechanisms of critical equipment. His focus is primarily on establishing root causes for repetitive failures and developing solutions to ensure reliable design for any given operating condition. Kittur earned an MS degree in solid mechanics and employs FEM-based structural and thermal simulations that are often required for a Level 3 API 579 fitness-for-service evaluation. Prior to joining Saudi Aramco, he was involved in a similar capacity for 10 yr in Canadian oil sands facilities.